Broadway Bridge to close for six months starting Oct. 13

Share this

(Note: the date has been corrected to October 13 for the closure)

Many North and Northeast Portland residents will need to change how they travel to and from downtown for six months.

The Broadway Bridge is one of the few connections over the Willamette River. It will close to all cars, trucks, and buses for maintenance work from Oct. 13 to April 11, 2026. The Portland Streetcar will detour around it to the Tilikum Crossing Bridge, increasing travel times.

Broadway Bridge closure in October
Broadway Bridge closure starting October 13.

The south sidewalk will remain open for cyclists, pedestrians and those using mobility devices during most of that time.

The work is part of the Broadway Bridge Lift Deck Replacement Project, which is being undertaken by Multnomah County. According to the county, the lift span deck is currently made of fiber-reinforced polymer structural members. The existing decking on the movable spans is retaining water and the structural beams have begun to fail. The deck and supporting beams will be replaced with concrete-filled steel. This is the same type of deck that can currently be found on the Morrison Bridge.

A contractor will replace the bridge deck – the driving surface – of the movable section of the bridge. To do the work, a contractor will remove small sections of the bridge deck, one at a time, to ensure that the movable bridge sections remain carefully balanced and can still be opened to river traffic as required by law. 

New streetcar tracks will also be installed in the section of the bridge deck being replaced. A and B loop streetcars will operate as one line, going both directions through downtown and along the central east side. The stop at NW 9th Ave. and Lovejoy St. will be closed for the duration of the project.

The project cost is estimated at $21.8 million. Multnomah County funded the design and 10% of the construction, with the federal government funding the other 90%.

The Broadway Bridge is one of five bridges over the Willamette River maintained by Multnomah County. The others are the Sellwood, Hawthorne, Morrison, and Burnside bridges, as well as the Wapato Bridge over the Multnomah Channel to Sauvie Island.

More information can be found here.