The Portland Bureau of Transportation (PBOT) has nearly completed ADA ramp construction on the N. Carey to N. Portsmouth segment of N. Willamette Blvd. Shortly after ADA ramps are finished, PBOT will grind, pave and restripe this segment’s road surface.

Photo courtesy of PBOT.
Paving is slated to begin on Monday, August 5, 2024, and will likely last three weeks although the schedule is weather dependent. If this timeline holds, cars will need to be moved off of N. Willamette Blvd. on or before Sunday, August 4th. “No Parking” signs will be placed along the corridor and physical mailers will be sent near the end of July. Please note that after construction is complete, parallel parking on N. Willamette Blvd. will no longer be allowed.
In addition to constructing ADA ramps, concrete bus waiting areas, wider bike lanes, and smoothing the pavement, PBOT will also add several new marked crosswalks across N. Willamette Blvd. Please view and share the project website for locations and details: Willametteblvd.com.
Current Schedule
Schedule below is tentative and will be periodically updated as design progresses.
- Through 2024: Design and right of way process continue for the Active Transportation Corridor Project
- Nearly complete: ADA curb ramp construction for the Paving and Striping Maintenance Project
- Underway now: Quick Build Bike Lane Extension Project construction
- Winter 2025: Design of the Active Transportation Corridor Project finishes, and project is published for construction contractor bidding process
- Summer 2025: Construction begins on the Active Transportation Corridor Project, likely lasting 12 months
Questions? Comments?
For more information, graphics, and the interactive map, please view (and share!) the project website: Willametteblvd.com
For questions and comments please get in touch with PBOT project manager below:
David Backes, Capital Project Manager, david.backes@portlandoregon, (503) 201-7575,
by Portland Bureau of Transportation