By Jim Redden
Southbound I-5 through the Rose Quarter reopened earlier than expected during the late night hours of Wednesday, Oct. 7.

The Oregon Department of Transportation first closed the lanes and on- and off-ramps on Tuesday, Sept. 11 as part of the long-planned I-5 Rose Quarter Improvement Project. The closure was originally planned to last until mid-October, but work went faster than expected because of the good weather, ODOT officials said.
The reopening was good news for North and Northeast Portland residents and business owners. According to ODOT, much of the southbound traffic diverted from I-5 went through area neighborhoods.
“We thank drivers, residents, businesses and organizations for your patience and effective efforts to navigate around the closure. Expect occasional ramp and lane closures as we restore lane striping, barriers and other traffic controls to their original configuration,” ODOT said when announcing the reopening.
The work included repairing and reinforcing weak areas, replacing bridge joints, repaving the surface, making safety improvements and repainting lane lines. Finishing work work expected to take 24 hours.
ODOT is planning a similar closure of all northbound lanes next year for similar work in 2027, but no dates have yet been announced.
Here were some of the reported neighborhood impacts:
- North Interstate Avenue in the southbound direction saw a 34% increase in travelers, with about 10,000 vehicles per day passing the intersection at North Graham Street, compared with 7,500 vehicles per day before the closure. Traffic speeds along the corridor have also declined during daylight hours, resulting in longer travel times.
- Northeast Martin Luther King Boulevard in the southbound direction saw a 34% increase in travelers, with about 29,000 vehicles per day passing by the intersection at Northeast Everett Street, compared with 22,000 vehicles per day before the closure.
- North Vancouver Avenue in the southbound direction saw a 54% increase in travelers, with about 8,000 vehicles per day passing by the intersection at North Mason Street, compared with 5,500 vehicles per day before the closure.
- The Steel Bridge in the westbound direction saw a 67% increase in travelers, with about 7,500 vehicles per day compared with 4,500 vehicles per day before the closure.
- Southwest Naito Parkway in the southbound direction saw a 35% increase in travelers, with about 8,500 vehicles per day passing by the intersection at Southwest Oak Street, compared with 6,000 vehicles per day before the closure.
- Data collected on neighborhood streets like Northeast 7th Avenue, Northeast Rodney Avenue, North Michigan Avenue, and North Flint Avenue show traffic volumes similar to weekdays before the closure.
More information is available on the project website at i5rosequarter.org/current-construction-travel-impacts.