Radius-Schnitzer violations spark hazardous fires

Share this
Radius Recycling - Schnitzer Steel scrap metal fire
Metal heap on fire at Radius Recycling – Schnitzer Steel scrap metal yard. Photo courtesy of Portland Fire & Rescue.

After towering scrap metal heaps caught fire twice this summer it has come to light that regulatory violations at the Radius-Schnitzer scrap metal facility (12005 N. Burgard Rd.) have exposed the community to toxic smoke. 

An Oregon Department of Environmental Quality (DEQ) permit for solid waste disposal sites has been required by law since 2019, giving the DEQ oversight of scrap yard operations. The permit requires best practices to avoid a potential fires that could affect the safety of residents, employees, firefighters and the environment.

Instead of complying, Radius-Schnitzer took legal action against DEQ, claiming it was exempt from the law and that the agency “lacked the authority” to require the permit. But on December 7, 2023, the Oregon Supreme Court disagreed and dismissed the claim in a letter. Since December 2023 the company has operated without a permit and has been out of compliance with the law.

Fires from the soaring scrap metal heaps are so hot and difficult to put out that they burn for many hours, often requiring emergency fire services for more than a day. The smoke is laden with metal particulate and carcinogens that could affect a 5-mile radius around the site, depending on wind direction and plume size. That would include most of the north peninsula, Linnton, NW Portland and Sauvie Island. The scrap yard is a mile and a half north of the St. Johns town center, and a half-mile from the nearest residences.

Map of 5-Mile radius around scrap metal yard at Radius Recycling-Schnitzer Steel
Map showing 5-Mile radius around scrap metal yard
at Radius Recycling-Schnitzer Steel

After the two recent fires, DEQ conducted site visits at the facility that resulted in a letter warning of “observed violations at the facility [that will be referred] to DEQ’s Office of Compliance and Enforcement for formal enforcement, which may include assessment of civil penalties and issuance of a compliance order.” 

The DEQ letter lists two serious violations:

Violation 1) Operating a disposal site without a disposal site permit from DEQ. “A permit is required by law because the nature, amount, and/or location of materials/activities can create a potential threat to the environment or public health.”

The list of situations and activities that require DEQ oversight are:

• Radius accepts waste materials that contain hazardous and toxic substances such as metals, oils, lead, mercury, and other hazardous substances.
• The facility is located adjacent to the Willamette River in a section of the river that has been declared a Superfund site.
• This facility uses a shredder to shred accepted waste materials. Shredding operations pose environmental risks such as creation of dust, runoff, releases or fires.
• Shredded wastes are stored in piles which can be exposed to stormwater, generate leachate, cause dust and pose a fire risk.
• Radius has had two fires in 2024 and informed DEQ that there are frequent fires in the waste piles.
• This site continues to process large quantities of materials per year.

The facility accepts waste tires, pressurized cylinders, appliances and other wastes that contain or potentially contain hazardous substances.

Violation 2) Radius is storing over 100 waste tires on site without operating under a waste tire storage site permit. The letter states that the company must submit a complete permit application. In the interim it must submit a plan to prevent fires from occurring in the piles.

The Office of Compliance and Enforcement could assess the company for civil penalties or a civil penalty for each day of violation.

A Radius Recycling spokesman was contacted for comment on the letter but did not respond by press time. 

Besides the threat of toxic smoke, there is also the cost to the public of putting out preventable scrap metal fires. The July 17th fire required a four-fire station response The media reported that around 100 firefighters battled the blaze for 6+ hours before being called off. A fire watch crew continued at the site until the next morning to control flare-ups. 

Critics ask what are the costs to the city in water and personnel in such an incident? And what are equipment costs including the two fire boats that were enlisted and a number of fire trucks? 

The North Peninsula Review will be working on researching these issues and will follow up this story with updates.